An addition to the Project Server 2007 SDK
Currently I’m working on a project which uses Microsoft Project Server 2007. However the SDK is poorly documented. Today I was looking at the Admin web service which can be used to configure settings on the server. In this post I’m not going in to detail how to do this, but I’ll share with you what I’ve discovered.
I’ve researched the connection between PWA’s “Task Settings and Display” page and the properties on the StatusingSettingsRow class which were not described. See the following image:
|
Name |
Description |
Enumeration |
|
WADMIN_DEFAULT_TRACKING_METHOD |
Specify the default method for reporting progress or tasks, and whether the tracking mode should be enforced on all projects. |
1 = Hours of work done per period. 2 = Percent of work complete. 3 = Actual work done and work remaining. |
|
WADMIN_IS_TRACKING_METHOD_LOCKED |
Force project managers to use the progress reporting method specified above for all projects. |
|
|
WADMIN_PROTECT_ACTUALS |
Restrict updates to Project Web Access. |
|
|
WADMIN_STAT_ENABLE_DOWNLOAD |
Enable ActiveX Gantt view for all users. |
|
|
WADMIN_STAT_LOOK_AHEAD |
Current tasks are those tasks which are not older than or further in the future more than this amount of days. |
|
|
WADMIN_STAT_TIMESHEET_TIED |
Time entry by Timesheet only. Users will sync to update tasks. |
|
|
WADMIN_TS_DEF_ENTRY_MODE_ENUM |
Specify how you want resources to report their hours. |
0 = Resources should report their hours worked every day. 1 = Resources should report their total hours worked for a week. |
|
WADMIN_WEEK_START_ON_ENUM |
Week starts on this day. |
0 = Sunday 1 = Monday 2 = Tuesday 3 = Wednesday 4 = Thursday 5 = Friday 6 = Saturday |